Crane Lift & Wide-Load Delivery in Cork: A Modular Home, On Time and On Budget

Delivering a modular home to a rural Cork site meant a wide-load escort, a 60-tonne crane, and a single lift over a mature hedgerow. Here's how we planned and executed the delivery — on time and on budget.

Share
Crane Lift & Wide-Load Delivery in Cork: A Modular Home, On Time and On Budget — Industry Insights article by New Chapter Homes Ireland

Looking for the full picture? Read our modular home prices guide.

A Modular Home for Rural Cork

Some deliveries are straightforward. This one wasn't — and that's exactly why it's worth telling.

A family in rural County Cork had ordered a Chapter One modular home to site on family land. The site was beautiful — a sloping field with views over the countryside — but it posed a genuine logistics challenge. The access lane was narrow, the final stretch involved a tight turn past a mature hedgerow, and the modular unit was too wide to travel without an escort. Getting a finished home from our Kildare workshop to that field, and onto its foundations, in one piece and on schedule, took serious planning.

This is the story of a crane lift and wide-load delivery — and how we delivered it on time and on budget, without compromise.

The Challenge: Wide-Load, Narrow Access

A modular home module of this size is classed as an abnormal load. That means:

  • A wide-load escort — pilot vehicles front and rear, warning other traffic and managing junctions.
  • Route surveying — every bridge, roundabout, narrow pinch point, and low overhead cable on the route from Kildare to Cork had to be checked and, where necessary, cleared.
  • Garda and local authority notification — permits for the movement, and coordination with TII for any national road sections.
  • A heavy crane on site — the module had to be lifted off the trailer, over the hedgerow that a vehicle couldn't pass, and down onto the prepared foundation on the sloping ground.

We planned the delivery over four weeks before a single lorry moved. The route was surveyed twice. The crane was booked — a 60-tonne mobile crane, sized for the lift radius and the module's weight. The foundation — ground screws, again, ideal for the sloping Cork ground — was installed and levelled the week before delivery.

Delivery Day: On the Road at Dawn

The convoy left Kildare at 5:00am. A pilot vehicle led, then the low-loader carrying the module, then a rear escort. The route had been chosen to avoid low bridges and the tightest Cork city approaches, running cross-country through Limerick and into West Cork.

Wide-load movement is slow, careful work. The convoy averaged well below the speed limit, with the escort vehicles managing overtaking traffic and the occasional tight village. By early afternoon, the low-loader was on site — the module intact, on schedule, and ready for the lift.

The Crane Lift: Over the Hedgerow

This was the moment everything hinged on. The modular home needed to come off the trailer, travel over a mature hedgerow that no vehicle could pass through, and be set down precisely on the ground-screw foundation on the sloping field beyond.

The 60-tonne crane was rigged and counterweighted. Slings were positioned at the engineered lift points on the module's steel chassis — the points our factory had designed specifically for this lift, so the structure's weight is distributed correctly and nothing flexes or distorts in the air.

Our banksman guided the operator by radio. The module lifted, swung slowly over the hedgerow — clearing it by a comfortable margin — and was lowered onto the foundation. Our team guided it into final position, checked level against the survey marks, and released the slings.

From lift-off to set-down: just under an hour. The hedgerow, the narrow access, the slope — all the things that would have made a traditional build on this site a slow, expensive ordeal — were irrelevant once the module was in the air. It simply went over them.

Connection and Finish

With the home set on its foundation, our crew spent the following two days completing the on-site work: connecting to the pre-prepped services (water, electricity, wastewater), finishing the external cladding and roof junctions, and running through the internal commissioning checks. The BER certificate and BCAR compliance pack were already in hand — the home had been certified at the factory.

On Time, and On Budget

The client moved in on the date we'd given them eight weeks earlier. The price was the price on the contract — no overruns for weather, no surprise crane-hire escalation, no "we found something in the ground" delays, because the ground screws went in in hours and the build itself never touched the site.

That's the promise of modular, and it's the promise we kept on this Cork project: a home delivered on time, and on budget, even when the delivery was genuinely hard.

Could We Deliver to Your Site?

Tight access, rural location, sloping ground, wide-load requirements — these aren't dealbreakers for us; they're logistics problems we plan and solve. If you have land in Cork, Kerry, Limerick, or anywhere in Ireland, and you've been told a modular home "couldn't get in," talk to us before you give up.

Contact us to arrange a free site survey and route assessment — we'll tell you honestly what's possible.

Ready to Start?

Talk to Our Team Today

Get expert advice, a free consultation, and a tailored quote for your project.

Get in Touch

Your Privacy & Cookie Consent

In accordance with the EU General Data Protection Regulation (GDPR) and the ePrivacy Directive, we use cookies and similar technologies to enhance your browsing experience, analyse site traffic, and personalise content. By clicking Accept All, you consent to our use of cookies. You may Decline to only allow strictly necessary cookies. For full details, see our Privacy Policy and Cookie Policy.